Future of The Fjords charging battery, Gudvangen

Operating, 2.4 MWh, power not stated, in Aurland. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gives.

The battery

Powernot stated by any source
Capacity2.4 MWh
What the sources say about the sizeMW not stated
KindFerry charging
StatusOperating, as of March 2026
Stated date2018, actual
What it is forcharges an electric ferry where the grid is too weak
MunicipalityAurland, Vestland
Bidding zoneNO5, the west (Bergen); read from its county
Placed on the mapGeoNames, Gudvangen

Who is behind it

No source read names who is behind it.

What the sources say

A floating battery pack at the quay that lets the Flåm to Gudvangen ferry charge quickly without a stronger grid. Not a market battery. NVE gives 2.4 MWh and no power figure.

Evidence and sources

Statnett publishes no meter, price or instruction per battery, so this page carries no money; what one megawatt would be paid in each reserve market is on the markets page. List id NO-B06.