Vitreous LabsEnergy transparency

Husøy grid battery (Smart Senja)

Operating, 2 MW and 2 MWh, in Senja, owned by Arva AS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gives.

The battery

Power2 MW
Capacity2 MWh
Duration1.0 hours
What the sources say about the sizeNVE gives 2 MW / 2 MWh at Husøy and 0.8 MW / 0.8 MWh at Senjahopen; the supplier described three units of 4.25 MVA and 3.79 MWh together, two of them on Husøy.
KindGrid support
StatusOperating, as of March 2026
Stated dateNovember 2021, actual
What it is forgrid support; ran the local grid as an island several times in storm Ingunn (2024)
MunicipalitySenja, Troms
Bidding zoneNO4, the north (Tromsø); read from its county
Placed on the mapGeoNames, Husøy (island)

Who is behind it

OwnerArva AS
Brønnøysund number979151950
Built or supplied byRolls-Royce (mtu EnergyPack)

What the sources say

Part of the Smart Senja pilot run by the grid company Arva. The 0.8 MW Senjahopen unit is under the one megawatt this list starts at and is left out.

Evidence and sources

Statnett publishes no meter, price or instruction per battery, so this page carries no money; what one megawatt would be paid in each reserve market is on the markets page. List id NO-B02.

All batteries  ·  On the map