Norway · the named batteries
Lysebotn 1 BESS
Applied for, 33 MW and 86 MWh, in Sandnes, owned by Lyse Kraft DA. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gives.
The battery
| Power | 33 MW |
| Capacity | 86 MWh |
| Duration | 2.6 hours |
| What the sources say about the size | 16 containers of 5.6 MWh; 40 MVA |
| Kind | Hybrid with a hydro plant |
| Status | Applied for, as of 21 August 2026 |
| What it is for | FFR, FCR, aFRR and mFRR with the 120 MW plant |
| Municipality | Sandnes, Rogaland |
| Bidding zone | NO2, the south west (Kristiansand, Stavanger); read from its county |
| Placed on the map | GeoNames, Lysebotn |
| NVE case | 26251, NVE reference 202612946 |
Who is behind it
| Owner | Lyse Kraft DA |
| Brønnøysund number | 925749419 |
| Group | Lyse and Hydro |
What the sources say
The largest battery any Norwegian concession paper names. Lyse also asked the grid company for a further 35 MW of draw and supply for it on 9 April 2026.
The papers on NVE’s case, newest first
- Situasjonsplan og 3D skisser (Konsesjon)
- Konsesjonssøknad (Konsesjon)
As NVE lists them on the case page, read every day; NVE’s document number rises with time. 2 papers in all.
Evidence and sources
- NVE case 26251: nve.no/konsesjon/konsesjonssaker/konsesjonssak
- Application (33 MW / 86 MWh): webfileservice.nve.no/API/PublishedFiles/Download/a0b88acc-90c8-4…
Statnett publishes no meter, price or instruction per battery, so this page carries no money; what one megawatt would be paid in each reserve market is on the markets page. List id NO-B14.