Valinor battery parks (first at Drangedal)

Announced, 40 MWh, power not stated, in Drangedal, owned by Valinor AS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gives.

The battery

Powernot stated by any source
Capacity40 MWh
What the sources say about the sizeAbout 40 MWh across three parks; no MW given.
KindStand-alone
StatusAnnounced, as of 24 October 2025
Stated date2026, expected
What it is forgrid support
MunicipalityDrangedal, Telemark
Bidding zoneNO2, the south west (Kristiansand, Stavanger); read from its county
Placed on the mapGeoNames, Drangedal municipality

Who is behind it

OwnerValinor AS
Brønnøysund number977362237
Built or supplied byElinor Batteries with Morlus

What the sources say

Three parks in southern Norway, one in Drangedal, investment up to NOK 80 million. No NVE case by title. A company named Drangedal Batteripark AS (938033323) was registered on 3 July 2026 at Norsk ESS's business address with Norsk ESS's purpose, word for word; whether it is this project is not said anywhere.

Evidence and sources

Statnett publishes no meter, price or instruction per battery, so this page carries no money; what one megawatt would be paid in each reserve market is on the markets page. List id NO-B22.