Cathkin Battery
50 MW, about 100 MWh (2 hours, from the capacity market de-rating class) in Stirlingshire and Fife. Everything on this page is read from published data for the 364 days to 11 November 2026, or is labelled as an estimate.
What it is
| Registered power | 50 MW balancing mechanism registration |
| Storage duration | 2 hours capacity market de-rating class |
| Charging zone | Stirlingshire and Fife |
| Connection site | Cathkin |
| Balancing mechanism unit | E_CATHB-1 |
Who owns it and who trades it
| Traded by | ENGIE Power Limitedconfirmed, Elexon's register |
| Owned by | CATHKIN ENERGY STORAGE LIMITED |
| Owner established from | capacity market registered holder |
| Ultimately | ENGIE confirmed source |
How we know. ENGIE bought Broxburn ready to build and operates Cathkin, per the development partners.
Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. Elexon's balancing mechanism unit register names the seller here and the name is checked against it on every build. How we tell them apart
What it is built from
| Battery system | Canadian Solar e-STORAGE, SolBank (LFP) |
| Engineering and construction | Canadian Solar e-STORAGE (EPC for both ENGIE sites) |
| Connection voltage | 33 kV documented: ENGIE's pair of Scottish 50 MW sites connect into the 33 kV network |
From published documents, not from any register: supplier and contractor project pages, owner announcements and the trade press. Confidence: stated per field. Checked 2026-08-31. source 1 · source 2. Fields not shown are not published anywhere we have found, and we do not guess them.
What it earned
| Line | 364 days to 11 November 2026 |
|---|---|
| Balancing mechanism | −£1.0m |
| Response and reserve auctions auction implied | £0 |
| Capacity market | £287k |
| Three lines together | not netted |
Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is the cleared price raised for inflation where the auction set a base period, split by month on EMRS's weights. Method
Outside the balancing mechanism, derived from the meter
Elexon publishes what this unit's meter recorded every half hour. Take away the balancing volumes NESO accepted and what is left is the position the unit ran outside the balancing mechanism: its wholesale trading, its frequency response delivery, and its losses, together. This unit held a frequency response contract in 57 of those half hours. The energy the contract asked of it, contracted megawatts times NESO's published delivery curve at the measured grid frequency, is taken out of the position and valued at the imbalance price, because it sits outside the unit's declared position and that is the price Elexon settles it at. What remains is the traded position, valued at the market index. The volumes are measured. The prices are public benchmarks, not this unit's trades. The product is derived, and is shown apart from the three measured lines above. 358 days to 5 November 2026, 42 of them still provisional in Elexon's settlement runs. Method and caveats
| Line | MWh or £ |
|---|---|
| Metered export, what crossed the meter out | 22,509 MWh |
| Metered import, what crossed the meter in | 26,258 MWh |
| Equivalent full cycles, everything sent out over one full charge | 226 over 358 days, 230 a year at that rate |
| Apparent meter to meter efficiency | 86%, an ordinary battery: round trip losses alone |
| Balancing offers accepted | 2,710 MWh |
| Balancing bids accepted | 12,500 MWh |
| Position outside balancing, export | 29,116 MWh |
| Position outside balancing, import | 23,076 MWh |
| Of which expected response delivery, net | −70 MWh 0 out, 70 in |
| Traded position, net | 6,111 MWh 29,141 out, 23,030 in |
| Traded position at the market index, sold | £4.6m |
| Traded position at the market index, bought | £2.3m |
| Traded position, net, at the index | £2.2m |
| Response delivery, net, at the imbalance price | −£14k −£14k at the index |
| Balancing and outside balancing together | £1.3m £26.81/kW/yr |
This battery connects to a distribution network. For such a unit the volumes Elexon publishes are settlement volumes: the site's own meter multiplied by the network operator's line loss factor for that half hour. The factor is usually within a few per cent of one, so the megawatt hours, cycles and efficiency above can sit a little above or below what crossed the site's meter. The money is settled on the same adjusted volumes. Method and caveats
When it moved, against when power was dear
Across every half hour this unit was metered the market index averaged £104.66. What it sent out was worth £156.85 a megawatt hour at that same index, 1.50 times the average. What it took in was worth £101.33, 0.97 times. Selling above one and buying below one is a unit positioned into the dear half hours and out of the cheap ones. It measures the half hours it chose, not the price anyone paid it, which is not published.
What it paid to buy energy back
When NESO accepts a bid, this unit delivers less than it had already sold, or takes more in. It pays for the energy it no longer delivers, and that payment is most of what makes the balancing figure above negative. Whether that is a cost or a margin depends on the price it paid. Across 12,500 MWh of accepted bids it paid an average of £101.31 a megawatt hour. The market index averaged £151.49 across those same half hours, so it bought back at £50.18 a megawatt hour below the going price.
| Price it paid | Volume | Average | Cash |
|---|---|---|---|
| below zero | 169 MWh | −£24.84 | £4k received |
| £0 to £25 | 445 MWh | £12.38 | £6k |
| £25 to £50 | 698 MWh | £38.77 | £27k |
| £50 to £75 | 1,420 MWh | £63.91 | £91k |
| £75 to £100 | 2,986 MWh | £88.19 | £263k |
| above £100 | 6,781 MWh | £130.36 | £884k |
On 169 MWh the price was below zero: NESO paid this unit an average of £24.84 a megawatt hour to take energy, £4k in all. That is a constrained network with more generation on it than it can move.
The other direction, offers, is much smaller here: 2,710 MWh where NESO asked for more, paid at an average of £131.28 against an index of £80.67.
Physical checks passed: the meter never exceeded the registered power by more than fifteen per cent, and the year's exports against imports are what a battery does.
Where it stands
| Balancing incomewhole fleet, £/kW/yr | 40th percentile103 units | |
| Balancing incomeScotland peer group | 56th percentile28 units | |
| Balancing income2.0 hour duration cohort | 27th percentile63 units | |
| All three measured lineswhole fleet, £/kW/yr | 25th percentile234 units | |
| Energy sent outhours at full power | 32nd percentile101 units | |
| Energy taken inhours at full power | 47th percentile101 units |
Percentiles, so 90 means better than nine in ten of the cohort named beside it, on that measure alone, over the same 364 days. Rates are pounds per kilowatt per year, annualised over the days the unit has been on the system, the same figures the performance league ranks on. A high position in the taken-in table is not a fault: a constraint asset is paid to charge, and charging is its job.
The nearest comparables
The five nearest in size in Scotland, and this battery among them, ranked by what each was paid for every kilowatt it holds over the 364 days to the same date. They run for about the same length of time. Same market, same rules, same weather.
| Battery | MW | Hours | Measured, per kW |
|---|---|---|---|
| Camilla | 49 | 1.5h | £99.7/kW/yr |
| Wishaw BESS | 51 | 2h | £40.4/kW/yr |
| East Ayrshire (KILSB-2) | 52 | 2h | £2.7/kW/yr |
| Shilton Lane BESS | 40 | 2h | £2.3/kW/yr |
| Erskine BESS | 30 | 2h | £1.6/kW/yr |
| Cathkin Batterythis battery | 50 | 2h | not netted |
The three lines are not added together for this site. It paid £1.4m to charge and the lines we can measure paid it £657k. The energy it bought was sold in the wholesale market and nothing published measures that sale, so subtracting one from the other would show a loss it does not make. Sites in this position are usually constraint assets, paid to absorb wind the network cannot move south.
In its distribution register
The distribution register of SP Energy Networks lists this site as Cathkin BESS, 61 MW, connected. Matched on the same owner, 0 km apart.
See it on the Development Atlas
From each operator’s embedded capacity register, read every Monday. How the registers are linked to the units that trade.
See it on the map
Every figure on this page traces to a published file. If something here is wrong about your asset, the methods section says how to tell us.
Need every battery at once? The register is not offered for automated download, and bulk access is by request at hello@vitreouslabs.com.