Minety South 2
46 MW, about 46 MWh (1 hour, published by Statera Energy) in Cotswold. Everything on this page is read from published data for the 364 days to 27 September 2026, or is labelled as an estimate.
What it is
| Registered power | 46 MW response and reserve auction registration |
| Storage duration | 1 hour published by Statera Energy |
| Charging zone | Cotswold |
| Connection site | Wiltshire |
| Balancing mechanism unit | 2__HSTAT002 a supplier unit registered by the company that trades it; its balancing actions are not yet counted on this site |
How this page was put together. Statera Energy runs two 50 MW batteries here, Minety South Storage and Minety South Storage 2, and Statkraft trades for Statera. NESO's auction results place one Statkraft battery code at Minety, AG-HSTK01. In 2,912 four hour blocks from 31 March 2025 NESO never bought more than 50 MW from it in either direction, and it sold 45 MW or more in two blocks of every five, which is what one 50 MW battery working close to its limit looks like. A second Statkraft battery code of about the same size in the same region, AG-HSTK02, is published with no postcode, and we have treated it as the second Minety South battery on that reasoning. Nothing published says which company sells under which code, so they are paired in order. Elexon registers the unit behind AG-HSTK01 at 100 MW, the one record that points the other way. If a document settles it, these pages change.
Who owns it and who trades it
| Traded by | Statkraft Markets GmbHruns several sitesconfirmed, Elexon's register |
| Owned by | MINETY SOUTH STORAGE 2 LTD |
| Owner established from | capacity market registered holder |
Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. Elexon's balancing mechanism unit register names the seller here and the name is checked against it on every build. How we tell them apart
What it earned
| Line | 364 days to 27 September 2026 |
|---|---|
| Balancing mechanism | not yet counted |
| Response and reserve auctions auction implied | £1.3m |
| Capacity market | £376k |
| Three lines together | £1.7m |
Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is the cleared price raised for inflation where the auction set a base period, split by month on EMRS's weights. Method
Outside the balancing mechanism, derived from the meter
Elexon publishes what this unit's meter recorded every half hour. Take away the balancing volumes NESO accepted and what is left is the position the unit ran outside the balancing mechanism: its wholesale trading, its frequency response delivery, and its losses, together. This unit held a frequency response contract in 3,167 of those half hours. The energy the contract asked of it, contracted megawatts times NESO's published delivery curve at the measured grid frequency, is taken out of the position and valued at the imbalance price, because it sits outside the unit's declared position and that is the price Elexon settles it at. What remains is the traded position, valued at the market index. In 1 half hours a contract was held but the grid frequency is not yet held, so those are left in the traded position. The volumes are measured. The prices are public benchmarks, not this unit's trades. The product is derived, and is shown apart from the three measured lines above. 88 days to 12 September 2026, 32 of them still provisional in Elexon's settlement runs. Method and caveats
| Line | MWh or £ |
|---|---|
| Metered export, what crossed the meter out | 2,670 MWh |
| Metered import, what crossed the meter in | 3,461 MWh |
| Equivalent full cycles, everything sent out over one full charge | 58.0 over 88 days, 241 a year at that rate |
| Apparent meter to meter efficiency | 77%, plausible: losses plus a standing load that is material against a modest throughput |
| Balancing offers accepted | 0 MWh |
| Balancing bids accepted | 0 MWh |
| Position outside balancing, export | 2,670 MWh |
| Position outside balancing, import | 3,461 MWh |
| Of which expected response delivery, net | 36 MWh 364 out, 328 in |
| Traded position, net | −828 MWh 2,542 out, 3,370 in |
| Traded position at the market index, sold | £342k |
| Traded position at the market index, bought | £309k |
| Traded position, net, at the index | £33k |
| Response delivery, net, at the imbalance price | £2k £4k at the index |
| Balancing and outside balancing together | £35k £3.16/kW/yr |
When it moved, against when power was dear
Across every half hour this unit was metered the market index averaged £116.56. What it sent out was worth £134.70 a megawatt hour at that same index, 1.16 times the average. What it took in was worth £91.83, 0.79 times. Selling above one and buying below one is a unit positioned into the dear half hours and out of the cheap ones. It measures the half hours it chose, not the price anyone paid it, which is not published.
Checks this unit did not pass cleanly. Published anyway, because a flagged figure with its flag is more use than a blank.
- only 88 of 364 days metered
Where it stands
| All three measured lineswhole fleet, £/kW/yr | 56th percentile229 units |
Percentiles, so 90 means better than nine in ten of the cohort named beside it, on that measure alone, over the same 364 days. Rates are pounds per kilowatt per year, annualised over the days the unit has been on the system, the same figures the performance league ranks on. A high position in the taken-in table is not a fault: a constraint asset is paid to charge, and charging is its job.
The nearest comparables
The five nearest in size in England and Wales, and this battery among them, ranked by what each was paid for every kilowatt it holds over the 364 days to the same date. They run for about the same length of time. Same market, same rules, same weather.
| Battery | MW | Hours | Measured, per kW |
|---|---|---|---|
| Gses 1 (GSET-07) | 45 | 1h | £41.9/kW/yr |
| Hunningley Stairfoot BESS | 44 | 1h | £37.0/kW/yr |
| Pivot Power Kemsley | 46 | 1h | £36.9/kW/yr |
| Minety South 2this battery | 46 | 1h | £36.4/kW/yr |
| Minety (AG-HLIM03) | 45 | 1h | £34.5/kW/yr |
| Nursling Battery Storage | 48 | 1h | £30.6/kW/yr |
See it on the map
Every figure on this page traces to a published file. If something here is wrong about your asset, the methods section says how to tell us.