Vitreous LabsEnergy transparency
Great Britain · the operating fleet

Hawkers Hill Battery

20 MW, about 40 MWh (2 hours, published by TagEnergy) in Somerset and Wessex. Everything on this page is read from published data for the 364 days to 11 November 2026, or is labelled as an estimate.

What it is

Registered power20 MW balancing mechanism registration
Storage duration2 hours published by TagEnergy
Charging zoneSomerset and Wessex
Connection siteHawkers Hill
Balancing mechanism unitE_HAWKB-1

Where the duration comes from. TagEnergy announced Hawkers Hill Energy Park, near Shaftesbury in Dorset, as 20 MW and 40 MWh, a two hour system built with Tesla Megapacks, when it began operating in September 2022 (Energy Global, 30 September 2022, energyglobal.com). Until 25 October 2026 this page gave 1.5 hours, the capacity market class, which is the duration an agreement was bid in. What the battery declares to NESO agrees with its owner: in the fullest 5% of 2,568 half hours from 1 September to 24 October 2026, the energy it held plus its room to charge came to 42 MWh, a little more than 40 MWh. Every megawatt hour figure on this site for this battery is worked from 2 hours.

Who owns it and who trades it

Traded byTesla Motors Limitedruns several sitesconfirmed, Elexon's register
Owned byHAWKERS HILL ENERGY PARK LIMITED
Owner established fromcapacity market registered holder
UltimatelyTagEnergy confirmed source

How we know. The control filing gives the company to TagEnergy UK Limited at three quarters or more with the right to appoint directors, since November 2020, and an individual held it before that. The capacity market agrees, holding a site called Hawkers Hill in the TagEnergy name 230 metres away. The registered office is RES's, which reflects who developed and administers it rather than who owns it.

Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. Elexon's balancing mechanism unit register names the seller here and the name is checked against it on every build. How we tell them apart

What it earned

Line364 days to 11 November 2026
Balancing mechanism£451k
Response and reserve auctions auction implied£0
Capacity market£229k
Three lines together£680k

Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is the cleared price raised for inflation where the auction set a base period, split by month on EMRS's weights. Method

Outside the balancing mechanism, derived from the meter

Elexon publishes what this unit's meter recorded every half hour. Take away the balancing volumes NESO accepted and what is left is the position the unit ran outside the balancing mechanism: its wholesale trading, its frequency response delivery, and its losses, together. This unit held a frequency response contract in 7,771 of those half hours. The energy the contract asked of it, contracted megawatts times NESO's published delivery curve at the measured grid frequency, is taken out of the position and valued at the imbalance price, because it sits outside the unit's declared position and that is the price Elexon settles it at. What remains is the traded position, valued at the market index. In 12 half hours a contract was held but the grid frequency is not yet held, so those are left in the traded position. The volumes are measured. The prices are public benchmarks, not this unit's trades. The product is derived, and is shown apart from the three measured lines above. 358 days to 5 November 2026, 42 of them still provisional in Elexon's settlement runs. Method and caveats

LineMWh or £
Metered export, what crossed the meter out15,072 MWh
Metered import, what crossed the meter in17,213 MWh
Equivalent full cycles, everything sent out over one full charge377 over 358 days, 384 a year at that rate
Apparent meter to meter efficiency88%, an ordinary battery: round trip losses alone
Balancing offers accepted11,799 MWh
Balancing bids accepted11,279 MWh
Position outside balancing, export13,075 MWh
Position outside balancing, import15,737 MWh
Of which expected response delivery, net−3,390 MWh 1,140 out, 4,530 in
Traded position, net728 MWh 13,536 out, 12,808 in
Traded position at the market index, sold£1.5m
Traded position at the market index, bought£1.0m
Traded position, net, at the index£512k
Response delivery, net, at the imbalance price−£342k −£324k at the index
Balancing and outside balancing together£651k £33.19/kW/yr

This battery connects to a distribution network. For such a unit the volumes Elexon publishes are settlement volumes: the site's own meter multiplied by the network operator's line loss factor for that half hour. The factor is usually within a few per cent of one, so the megawatt hours, cycles and efficiency above can sit a little above or below what crossed the site's meter. The money is settled on the same adjusted volumes. Method and caveats

When it moved, against when power was dear

Across every half hour this unit was metered the market index averaged £104.66. What it sent out was worth £112.58 a megawatt hour at that same index, 1.08 times the average. What it took in was worth £78.96, 0.76 times. Selling above one and buying below one is a unit positioned into the dear half hours and out of the cheap ones. It measures the half hours it chose, not the price anyone paid it, which is not published.

What it paid to buy energy back

When NESO accepts a bid, this unit delivers less than it had already sold, or takes more in. It pays for the energy it no longer delivers, and that payment is most of what makes the balancing figure above negative. Whether that is a cost or a margin depends on the price it paid. Across 11,279 MWh of accepted bids it paid an average of £79.00 a megawatt hour. The market index averaged £101.99 across those same half hours, so it bought back at £22.99 a megawatt hour below the going price.

Price it paidVolumeAverageCash
below zero463 MWh−£18.79£9k received
£0 to £25478 MWh£13.28£6k
£25 to £50730 MWh£38.58£28k
£50 to £752,623 MWh£65.12£171k
£75 to £1004,563 MWh£87.74£400k
above £1002,422 MWh£121.43£294k

On 463 MWh the price was below zero: NESO paid this unit an average of £18.79 a megawatt hour to take energy, £9k in all. That is a constrained network with more generation on it than it can move.

The other direction, offers, is much smaller here: 11,799 MWh where NESO asked for more, paid at an average of £116.21 against an index of £86.91.

Physical checks passed: the meter never exceeded the registered power by more than fifteen per cent, and the year's exports against imports are what a battery does.

Where it stands

Balancing incomewhole fleet, £/kW/yr87th percentile103 units
Balancing incomeEngland and Wales peer group82nd percentile75 units
Balancing income2.0 hour duration cohort82nd percentile63 units
Balancing incomebatteries sold by Tesla Motors Limited86th percentile15 units
All three measured lineswhole fleet, £/kW/yr84th percentile234 units
Energy sent outhours at full power91st percentile101 units
Energy taken inhours at full power83rd percentile101 units

Percentiles, so 90 means better than nine in ten of the cohort named beside it, on that measure alone, over the same 364 days. Rates are pounds per kilowatt per year, annualised over the days the unit has been on the system, the same figures the performance league ranks on. A high position in the taken-in table is not a fault: a constraint asset is paid to charge, and charging is its job.

The nearest comparables

The five nearest in size in England and Wales, and this battery among them, ranked by what each was paid for every kilowatt it holds over the 364 days to the same date. They run for about the same length of time. Same market, same rules, same weather.

BatteryMWHoursMeasured, per kW
Oldham BESS202h£78.5/kW/yr
Willoughby201.5h£69.9/kW/yr
Carnegie Road 1202h£56.3/kW/yr
Feeder Road201.5h£53.8/kW/yr
Farnham BESS202h£35.0/kW/yr
Hawkers Hill Batterythis battery202h£34.1/kW/yr

See it on the map

Open the operating map here

Every figure on this page traces to a published file. If something here is wrong about your asset, the methods section says how to tell us.

Need every battery at once? The register is not offered for automated download, and bulk access is by request at hello@vitreouslabs.com.