Being built, 700 MW · 2,800 MWh, in Dilsen-Stokkem, owned by GIGA Storage. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 700 MW |
| Capacity | 2,800 MWh |
| Duration | 4.0 hours |
| Status | Being built, as of 19 October 2026 |
| Owner’s date | March 2028, expected by the end of March 2028 |
| Municipality | Dilsen-Stokkem, Rotem, Limburg |
| Grid connection | Elia, a new substation on the site |
| Placed on the map | at Rotem, the place its source names, in Dilsen-Stokkem (GeoNames) |
Who is behind it
| Owner | GIGA Storage |
| Built by | Tesla (640 Megapack 3) |
Not published anywhere we have found: ultimate owner, developer, traded by. The page says so rather than guessing.
Not in Elia’s list
Elia does not schedule this battery, because it is not yet running.
What the sources say
Earlier announced at 600 MW and 2,400 MWh. Preparatory works began in mid August 2026. RWE cancelled a different 200 MW battery in the same area in June 2023.
Evidence and sources
- owner: enerdata.net/publications/daily-energy-news/giga-storage-sec…
- status: driveteslacanada.ca/news/tesla-megapacks-belgium-green-turtle-const…