Theilheim Speicher BA III Ino

4.6 MW, 14 MWh (3 hours) in Theilheim, Bayern, registered as operating since 20 September 2023. Everything on this page is read from Germany’s register of power units and the other published records named beside each fact.

What it is

The register holds this battery as two units.

UnitRegister numberMWMWhCommissionedBatteryGrid operator check
Theilheim Speicher BA III InoSEE9503344411023.18.320 October 2026727under check
Theilheim, Speicher 1SEE9296469745161.55.520 September 2023727checked

Power is the net power the operator registered, the most the unit may feed into the grid. Energy is the usable capacity of the unit’s installation. A grid operator check marked “checked” means the grid company has confirmed the entry; “under check” means it has not yet. On the large sites we compared, the register’s commissioning date often came months before the owner’s announced start, which suggests it records first energisation.

Who runs it and who owns it

Operator in the registerCommercial register entry, as the operator gave itSeat
Suntec Energiesysteme GmbHAmtsgericht Würzburg HRB 8649Gaukönigshofen, Bayern
SunTec Solarpark GmbH & Co. VII KGAmtsgericht Würzburg HRA 8129Gaukönigshofen, Bayern

We have not yet traced the owner behind Suntec Energiesysteme GmbH and SunTec Solarpark GmbH & Co. VII KG. The commercial register holds it, and the owners page lists every family traced so far.

The register names the operator, the company that runs the unit. The owner behind it comes from the commercial register (Handelsregister) or the owner’s own publication, as marked. The register number is the one the operator typed in; on 11 October 2026 we found it wrong or missing for 26 of the companies we looked up.

Who trades it and what it is built from

No published source we have found names who trades this battery, who built it or whose cells it uses. Fields we cannot source are left out.

Where it connects

Grid companyMainfranken Netze GmbH and N-ERGIE Netz GmbH
Connected atmedium voltage
MunicipalityTheilheim, district of Würzburg
StateBayern
Land parcelTheilheim, 5518; Theilheim, 5522
Registered position49.7583, 10.0561
Register locationSEL951261658267, SEL991534893957

As registered. The grid company and voltage come from the register’s public unit table; the position is the one the operator registered. See it on the Atlas.

Tender award

UnitAwardAnnouncedBidderMW bid
Theilheim Speicher BA III InoInn25-1/03010 July 2025Suntec Energiesysteme GmbH11
Theilheim, Speicher 1Inn21-1/0397 May 2021Suntec Energiesysteme GmbH0

The innovation tenders pay a market premium to solar or wind paired with storage. The award lists are the Bundesnetzagentur’s. A bidder that differs from today’s operator dates a change of hands, or a spelling difference.

What has changed in the register

First registered on 25 September 2023; last changed in the register on 16 November 2026.

SeenUnitWhat changedFromTo
13 October 2026Theilheim Speicher BA III InoGross power3 MW3.1 MW
13 October 2026Theilheim Speicher BA III InoNet power3 MW3.1 MW
13 October 2026Theilheim Speicher BA III InoPlanned date18 August 202519 October 2026
13 October 2026Theilheim Speicher BA III InoTender awardblankInn25-1/030
15 October 2026Theilheim Speicher BA III InoNet power3 MW3.1 MW
15 October 2026Theilheim Speicher BA III InoPlanned date18 August 202519 October 2026
21 October 2026Theilheim Speicher BA III InoBetriebsStatusId3135
21 October 2026Theilheim Speicher BA III InoCommissioning dateblank20 October 2026
21 October 2026Theilheim Speicher BA III InoEegAnlageRegistrierungsdatum22 August 202420 October 2026
21 October 2026Theilheim Speicher BA III InoEegInbetriebnahmeDatumblank20 October 2026
21 October 2026Theilheim Speicher BA III InoEinheitRegistrierungsdatum22 August 202420 October 2026
21 October 2026Theilheim Speicher BA III InoPlanned date19 October 2026blank
21 October 2026Theilheim Speicher BA III InoRegister locationblankSEL991534893957
21 October 2026Theilheim Speicher BA III InoRegister location idblank10469999
21 October 2026Theilheim Speicher BA III InoStatusIn PlanungIn Betrieb
24 November 2026Theilheim Speicher BA III InoCommissioning date20 October 2026
24 November 2026Theilheim Speicher BA III InoNet power3.1 MW3.1 MW
24 November 2026Theilheim Speicher BA III InoPlanned date19 October 2026
24 November 2026Theilheim Speicher BA III InoStatusIn PlanungIn Betrieb
24 November 2026Theilheim, Speicher 1Net power1.5 MW1.5 MW

What this page cannot show

Germany publishes no battery’s metered output. On 11 October 2026 we checked the four public sources that might carry it: the ENTSO-E Transparency Platform, SMARD, the yearly EEG data and the transmission companies’ redispatch records. None gives the output of any German battery, one by one or as a fleet. So this page cannot say what the battery exported, imported or earned, as Britain’s battery pages do.

Sources: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland, Namensnennung 2.0: the register as read on 24 November 2026 and the public unit table of 24 November 2026. Company details from the register’s market actor table. Owners from the commercial register and the owners’ publications, as marked. Tender awards from the Bundesnetzagentur’s award lists.