Gørlev battery

Announced, 30 MW · 60 MWh, in Kalundborg Municipality, owned by BME BPP 1 ApS. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power30 MW
Capacity60 MWh
Duration2.0 hours
StatusAnnounced, as of 20 August 2025
Bidding zoneDK2, East Denmark
MunicipalityKalundborg
Address in the permitGørlev Landevej 7
Placed on the mapat the address its permit gives (Gørlev Landevej 7), found on OpenStreetMap
Nearest transmission stationHejninge (132 kV), 14 km away: 478 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026

Who is behind it

OwnerBME BPP 1 ApS

Not published anywhere we have found: ultimate owner, developer, built by, optimiser.

What the sources say

Screening decision of 20 August 2025. It may overlap the Sæbyhøjvej (Høng) row, which also connects at Sæby.

Evidence and sources

From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B050.