Lisbjerg battery (Kredsløb)
Announced, 5 MW · 10 MWh, in Aarhus Municipality, owned by Kredsløb Halmenergi A/S. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 5 MW |
| Capacity | 10 MWh |
| Duration | 2.0 hours |
| Status | Announced, as of 16 August 2026 |
| Bidding zone | DK1, West Denmark |
| Municipality | Aarhus |
| Placed on the map | at Lisbjerg, the place its source names (GeoNames) |
| Nearest transmission station | Mollerup (150 kV), 2 km away: 185 MW for new production on the grid as it is, 0 MW for new consumption, in Energinet’s map of 1 February 2026 |
Who is behind it
| Owner | Kredsløb Halmenergi A/S |
Not published anywhere we have found: ultimate owner, developer, built by, optimiser.
What the sources say
Supply tender published 16 August 2026 (deadline 15 September 2026): 5 MW, at least 10 MWh usable. Award not found (tender aggregator only).
Evidence and sources
From owners’, developers’ and builders’ own releases and municipal and environmental permits, read by Vitreous; where a field rests on the trade press alone, the notes say so. Energinet publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Energinet’s markets is on the markets page, for the whole market and never for a named battery. The nearest transmission station is the nearest by distance on Energinet’s capacity map; where the battery actually connects is not published. List id DK-B062.