Vitreous LabsEnergy transparency

Pedersöre (Ingrid Capacity)

Announced, 45 MW · 90 MWh, in Pedersöre, owned by Ingrid Capacity with Mirova (partnership). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power45 MW
Capacity90 MWh
Duration2.0 hours
StatusAnnounced, as of 23 September 2026
MunicipalityPedersöre
Placed on the mapat the centre of Pedersöre, its municipality (GeoNames)

Who is behind it

OwnerIngrid Capacity with Mirova (partnership)
DeveloperIngrid Capacity

Ingrid Capacity (Sweden) and Mirova (France). YTJ lists Ingrid Capacity Finland 2, 3 and 5 Oy; no source ties one to Pedersöre.

Not published anywhere we have found: ultimate owner, built by, cells. The page says so rather than guessing.

What the sources say

Ingrid (23 Sep 2026): 45 MW / 90 MWh, ready to build, with an offtake agreement; Ingrid develops, operates and optimises.

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B050.

All batteries  ·  On the map