Simo, phase 1

Operating, 30 MW · 60 MWh, in Simo, owned by Joint venture of FRV and AMP Tank Finland Oy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power30 MW
Capacity60 MWh
Duration2.0 hours
StatusOperating, as of 16 May 2025
Owner’s dateMay 2025, actual
MunicipalitySimo
Grid connectionNear Fingrid Simojoki substation
Placed on the mapat the centre of Simo, its municipality (GeoNames)

Who is behind it

OwnerJoint venture of FRV and AMP Tank Finland Oy
Ultimate ownerFRV is part of Jameel Energy (ESS News only)
DeveloperThe FRV and AMP Tank joint venture
Built bySungrow (PowerTitan LFP containers)

A joint venture. AMP Tank Finland Oy is 3199785-1. YTJ lists FRV AmpTank I Oy (3315364-4) by name only; no source ties it to this battery.

Not published anywhere we have found: cells. The page says so rather than guessing.

What the sources say

Status rests on Sungrow's word: "successful deployment" of 30 MW / 60 MWh on 16 May 2025. FRV's own Simo page (read 12 Oct 2026) still says phase 1 was "expected to be operative in Q1 2025" and gives the whole project as "In construction". Unit count: 26 (Sungrow; FRV page) against 24 (FRV release of Nov 2024). Energy-Storage.news (29 May 2025) is no longer used.

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B009.