Teuva (Prime Capital, from Usva Energia)
Announced, 100 MW, in Teuva, owned by Prime Green Energy Infrastructure Fund II, managed by Prime Capital AG. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 100 MW |
| Status | Announced, as of 17 March 2026 |
| Municipality | Teuva |
| Placed on the map | at the centre of Teuva, its municipality (GeoNames) |
Who is behind it
| Owner | Prime Green Energy Infrastructure Fund II, managed by Prime Capital AG |
| Developer | Usva Energia |
No source names the company that holds it. Possible project company in YTJ, by name only: Teuva Energy Storage Oy (3530156-7, former name Usva Energy Storage Teuva Oy).
Not published anywhere we have found: ultimate owner, built by, cells. The page says so rather than guessing.
What the sources say
Usva (17 Mar 2026): sale of the 100 MW ready-to-build project in Teuva closed. MWh not stated.
Evidence and sources
From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B043.