Germany’s battery queue

This report counts Germany’s grid batteries from the regulator’s register. It sets them against what the power market paid, the 574 GW queue and the rules that decide which batteries get built.
A count of Germany’s grid batteries and the queue behind them. Winter 2026, 21 pages, A4. Every figure is measured from a named source, and the sources are listed at the back.
In brief
4.6 GW
of batteries of 1 MW and more ran in Germany on 23 November 2026, 79% more than at the end of 2025.
Marktstammdatenregister
€28 and €203
the average summer price per MWh at 1pm and at 8pm.
SMARD day-ahead prices
€89,000
per MW a year: the most a two-hour battery could have made on the day-ahead auction, before costs.
Vitreous calculation on SMARD prices
574 GW
of batteries asked for a grid connection in 2025, 124 times the battery power Germany runs.
Bundesnetzagentur, on SMARD
1 January 2027
Under the regulator’s draft, a battery that commits after this date will pay grid fees.
Bundesnetzagentur draft (AgNes)
1.35 GW
of batteries could bid for the fastest reserve at the start of 2026. Germany buys 584 MW of it.
Transmission companies; trade sources
70%
of each day’s cheapest quarter hours fell between 10:00 and 17:00, so batteries mostly store midday solar power.
SMARD day-ahead prices
25%
of running battery power stands in Bavaria and Baden-Württemberg.
Marktstammdatenregister
What is inside
- 1The shape of the marketWhy evening power costs far more than midday power
- 2What has been builtThe fleet year by year, the largest sites and who owns them
- 3What batteries earnSpreads, reserve markets and one owner’s accounts
- 4The queueRequests, offers and the register’s planned list
- 5December’s deadlinesThe maturity procedure and the grid fee cut-off
- 6Where batteries connectEvery battery on the map of the grid
- 7North and southWhether batteries ease the old bottleneck
- 8What to watchDates from January 2027