FlevoBESS (Dronter Energie Opslag)

Operating, 32 MW · 126 MWh, in Dronten, owned by Flevo-BESS B.V. (XY Wind, Ansjovisstroom, Flevo Ventum; 400+ local shareholders). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power32 MW
Capacity126 MWh
Duration4.0 hours
StatusOperating, as of 20 October 2026
Stated dateDecember 2025, put into operation in December 2025, by the Dronter Energie Opslag site
MunicipalityDronten, Flevoland
Grid connectionGesloten Distributiesysteem Groen at Windplan Groen transformer station, connected to TenneT; GDG Groen station
Placed on the mapat the site itself, as mapped on OpenStreetMap (FlevoBESS)
How sureA dated source confirms it

Who is behind it

OwnerFlevo-BESS B.V. (XY Wind, Ansjovisstroom, Flevo Ventum; 400+ local shareholders)
Traded byEneco (long-term lease, ASN Bank)
Built byAlfen

What the sources say

No dated source found that confirms operation. Modo (17 September 2026) counts 168 MW at six Flevoland sites, which matches this list's Flevoland total only if FlevoBESS and Zeewolde are counted as operating. That is indirect support, not confirmation.; Status kept at construction because the last dated source (8 October 2025) says it was being built. It is probably running by now, but no source says so. Probable.

Evidence and sources

From the owners’, developers’ and builders’ own releases, grid operators’ and permit notices and the trade press, read by Vitreous. No Dutch body publishes a meter, an instruction or a payment for a named battery, so this page carries none. List id NL-B22.