Vitreous LabsEnergy transparency
Great Britain · the operating fleet

Thornton Battery

200 MW, about 400 MWh (2 hours, published by Statkraft) in South Lancashire, Yorkshire and Humber. Everything on this page is read from published data for the 364 days to 22 November 2026, or is labelled as an estimate.

What it is

Registered power200 MW balancing mechanism registration
Storage duration2 hours published by Statkraft
Charging zoneSouth Lancashire, Yorkshire and Humber
Connection siteThornton 400kV
PostcodeYO42
Balancing mechanism unitT_BLWNB-1

Where the duration comes from. Statkraft describes Thornton Greener Grid Park as a 200 MW two hour battery (statkraft.co.uk). Statkraft has not published a figure in MWh; the 400 MWh on this page is 200 MW for two hours. Every megawatt hour figure on this site for this battery is worked from 2 hours.

Who owns it and who trades it

Traded byStatkraft Markets Gmbhruns several sitesconfirmed, Elexon's register
Owned bynot published anywhere we can read
UltimatelyStatkraft confirmed source

How we know. The register names no owner. Statkraft built Thornton Greener Grid Park, 200 MW, and its trading company Statkraft Markets GmbH is the lead party.

Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. Elexon's balancing mechanism unit register names the seller here and the name is checked against it on every build. How we tell them apart

What it earned

Line364 days to 22 November 2026
Balancing mechanism−£744k
Response and reserve auctions auction implied£201k
Capacity marketno agreement we can attach
Three lines togethernot netted

Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is the cleared price raised for inflation where the auction set a base period, split by month on EMRS's weights. Method

Outside the balancing mechanism, derived from the meter

Elexon publishes what this unit's meter recorded every half hour. Take away the balancing volumes NESO accepted and what is left is the position the unit ran outside the balancing mechanism: its wholesale trading, its frequency response delivery, and its losses, together. This unit held no frequency response contract in the window, so the whole position is treated as traded. The volumes are measured. The prices are public benchmarks, not this unit's trades. The product is derived, and is shown apart from the three measured lines above. 281 days to 5 November 2026, 42 of them still provisional in Elexon's settlement runs. Method and caveats

LineMWh or £
Metered export, what crossed the meter out20,205 MWh
Metered import, what crossed the meter in26,802 MWh
Equivalent full cycles, everything sent out over one full charge50.5 over 281 days, 65.6 a year at that rate
Apparent meter to meter efficiency75%, worth investigating: more than ordinary losses
Balancing offers accepted8,312 MWh
Balancing bids accepted10,521 MWh
Position outside balancing, export23,623 MWh
Position outside balancing, import28,011 MWh
Valued at the market index, sold£4.4m
Valued at the market index, bought£3.4m
Outside balancing, net, at the index£955k
Balancing and outside balancing together£737k £4.79/kW/yr

When it moved, against when power was dear

Across every half hour this unit was metered the market index averaged £110.32. What it sent out was worth £184.82 a megawatt hour at that same index, 1.68 times the average. What it took in was worth £121.78, 1.10 times. Selling above one and buying below one is a unit positioned into the dear half hours and out of the cheap ones. It measures the half hours it chose, not the price anyone paid it, which is not published.

What it paid to buy energy back

When NESO accepts a bid, this unit delivers less than it had already sold, or takes more in. It pays for the energy it no longer delivers, and that payment is most of what makes the balancing figure above negative. Whether that is a cost or a margin depends on the price it paid. Across 10,521 MWh of accepted bids it paid an average of £144.38 a megawatt hour. The market index averaged £191.34 across those same half hours, so it bought back at £46.96 a megawatt hour below the going price.

Price it paidVolumeAverageCash
below zero116 MWh−£10.87£1k received
£0 to £25247 MWh£14.37£4k
£25 to £50362 MWh£35.15£13k
£50 to £75266 MWh£67.15£18k
£75 to £100698 MWh£88.07£61k
above £1008,833 MWh£161.30£1.4m

On 116 MWh the price was below zero: NESO paid this unit an average of £10.87 a megawatt hour to take energy, £1k in all. That is a constrained network with more generation on it than it can move.

The other direction, offers, is much smaller here: 8,312 MWh where NESO asked for more, paid at an average of £156.57 against an index of £103.95.

Checks this unit did not pass cleanly. Published anyway, because a flagged figure with its flag is more use than a blank.

  • only 281 of 364 days metered

Where it stands

Balancing incomewhole fleet, £/kW/yr92nd percentile103 units
Balancing incomeEngland and Wales peer group89th percentile75 units
Balancing income2.0 hour duration cohort90th percentile63 units
All three measured lineswhole fleet, £/kW/yr21st percentile234 units
Energy sent outhours at full power31st percentile102 units
Energy taken inhours at full power17th percentile102 units

Percentiles, so 90 means better than nine in ten of the cohort named beside it, on that measure alone, over the same 364 days. Rates are pounds per kilowatt per year, annualised over the days the unit has been on the system, the same figures the performance league ranks on. A high position in the taken-in table is not a fault: a constraint asset is paid to charge, and charging is its job.

The nearest comparables

The five nearest in size in England and Wales, and this battery among them, ranked by what each was paid for every kilowatt it holds over the 364 days to the same date. They run for about the same length of time. Same market, same rules, same weather.

BatteryMWHoursMeasured, per kW
Thurrock Flexible (THURB-1)1002h£74.9/kW/yr
Thurrock Flexible (THURB-3)1002h£45.1/kW/yr
Dollymans Storage1022h£44.2/kW/yr
Thurrock Flexible (THURB-2)1002h£27.7/kW/yr
Lakeside BESS1052h£26.8/kW/yr
Thornton Batterythis battery2002hnot netted

The three lines are not added together for this site. It paid £2.6m to charge and the lines we can measure paid it £2.1m. The energy it bought was sold in the wholesale market and nothing published measures that sale, so subtracting one from the other would show a loss it does not make.

See it on the map

Open the operating map here